Key Takeaways
- A delay claim usually stands or falls on paperwork: notices sent on time in the form the contract demands, and careful records of what happened on site. UAE courts work from civil law, but common law ideas also play a part in some forums.
- To win, you have to show that the event caused the delay, put an exact figure on the loss and follow the procedure of the forum hearing the case, be it DIAC (the Dubai International Arbitration Centre), another arbitration centre or a local court.
- Getting a lawyer involved early makes a real difference to the result.
Dubai towers and Abu Dhabi infrastructure projects run late all the time, and many of those delays turn into legal disputes. How you handle a delay claim can decide whether you recover millions in damages or lose your position under the contract altogether. Below you'll find the evidence you need, the steps you have to follow and the decisions you'll face, whether your company is the developer, the main contractor or a subcontractor.
Browse our UAE lawyer directory to find lawyers who handle construction disputes and delay analysis.
Which laws apply to a construction delay in the UAE
That depends on where the project is. The UAE runs two kinds of legal system side by side, and this changes how a delay claim gets decided. Onshore projects, meaning those outside the financial free zones, fall under two federal laws. The first is the Civil Transactions Law (Federal Decree-Law No. 25 of 2025). It has been in force since 1 June 2026 and replaced Federal Law No. 5 of 1985 for legal effects arising from that date. The second is the Civil Procedure Law (Federal Decree-Law No. 42 of 2022), which sets out how court cases run. Free zone projects, particularly those in the Dubai International Financial Centre (DIFC) and Abu Dhabi Global Market (ADGM), are different. These zones have their own independent courts, and they apply common law, the English system where judges follow earlier decisions.
What you must prove under onshore civil law
The Civil Transactions Code is the basis for any compensation claim. You have to prove the breach or harmful act, the damage and the causal link between the two. This is hard for subcontractors. A subcontractor has no contract with the developer, so it has no contractual claim against it. It can only claim for a harmful act, and then it must prove the act, the damage and the causal link itself. That's why construction delay claims in the UAE are a real challenge for subcontractors who never signed anything with the developer.
Force majeure, an outside event nobody could foresee or prevent, has its own meaning under the Civil Transactions Code. If the event makes performance impossible, the obligation ends. If an exceptional general event only makes performance far more burdensome, the court can reduce the obligation instead. That second rule is known as hardship (Article 249 of the 1985 law; Article 224 of the 2025 law, which also allows rescission, meaning the contract is cancelled). Delay claims from the COVID-19 period often came down to which of the two fitted the facts.
How the DIFC and ADGM courts differ
Both courts work on a common law basis. ADGM applies English common law directly. DIFC has its own written laws and falls back on English law where they're silent. So you can argue common law doctrines there, such as the prevention principle (an employer can't hold you to a deadline it stopped you from meeting) and the various approaches to concurrent delay, where both sides caused delay over the same period. The forum can help or hurt you, depending on what your claim looks like. Common law forums may be more open to detailed delay analysis methods such as time impact analysis and collapsed as-built scheduling. Onshore, the experts the court appoints often prefer a simpler critical path demonstration. The critical path is the chain of tasks that sets the project's finish date.
Notice rules that keep your claim alive
Most UAE projects use standard contract forms. Many are based on FIDIC, the International Federation of Consulting Engineers, whose templates get adapted for local use. These forms set strict notice rules that catch contractors off guard. If you don't comply, you usually lose the right to claim for the delay, however good the claim is.
Notice deadlines
Most UAE construction contracts require you to:
- give written notice of a delay event promptly, which means within 28 days of becoming aware of it under FIDIC 1999 Sub-Clause 20.1 and FIDIC 2017 Sub-Clause 20.2
- send detailed particulars within 42 days (FIDIC 1999) or 84 days (FIDIC 2017)
- submit the final claim within the windows the contract sets after the project is finished
FIDIC 1999 Sub-Clause 20.1 contains a "time bar", a rule that cuts off any claim not notified in time. It's used widely on UAE projects and has led to a lot of litigation. How strictly UAE courts and tribunals apply it depends on the facts and on the law that governs the contract. Don't count on leniency.
What a valid notice has to say
A delay notice should identify:
- the contract clause you say was breached, or the event that triggered the claim
- how long the delay is expected to last or has lasted, with an early critical path analysis
- the contractual and legal grounds for the relief you're asking for
- a reservation of your right to put a figure on the claim later
Construction lawyers often advise sending "protective notices". These are broad notices that keep every possible claim open, even before you have the full details. They also help show that you tried in good faith to comply at a time when the other side knew more than you did.
Gathering evidence and analysing the delay
UAE courts and tribunals look hard at delay evidence. You'll need detailed, forensic-level records and an expert analysis that holds up on the technical side as well as the legal one.
Records to keep in your claim file
A delay claim file should include:
| Item | Details |
|---|---|
| Baseline schedules | The construction programs as approved, showing resources and the logic links between tasks |
| Progress records | Daily reports, photos, inspection records and milestone certificates |
| Correspondence archives | Every request for information (RFI), submittal, variation instruction and set of meeting minutes |
| Cost records | A detailed breakdown of extended site overheads, idle equipment and the cost of speeding up work |
| Weather and external data | Weather records, government announcements and reports by third parties |
Delay analysis methods the tribunals accept
UAE courts and tribunals accept several ways of analysing delay. Which one they prefer depends on the forum.
Impacted as-planned analysis. It's popular because it's easy to follow. You take the original schedule and show how particular events would have pushed it back. The weak spot is that it ignores concurrent delays and changes to the real order of work, and the other side will point that out.
Time impact analysis. International arbitration often prefers this method. The schedule is updated to show actual progress at the moment each delay event happened, and then the event is added to measure its own effect. You need skilled schedulers, specialist software and records made at the time.
Collapsed as-built. This starts from the order in which the work was really done and takes the delay events out, to show when you'd have finished "but for" them. It's hard to do well, and the other side may attack the hypothetical rebuild.
A lawyer who understands scheduling, or who works closely with a delay analyst, can make sure the method you pick matches the evidence you actually have and what the forum prefers.
The dispute steps and how to plan for them
UAE construction contracts usually set out several dispute steps, one after another. How you handle each step has a big effect on the outcome of the claim.
The Engineer's determination and dispute boards
FIDIC-based contracts require a determination from the Engineer, the contract administrator named in the contract, before you can go to arbitration. Contractors in the UAE don't always follow this. Some skip the step because they think the Engineer is biased, and then face procedural objections. Many projects also require a Dispute Adjudication Board (DAB), a panel that decides disputes while the project is still running. Its rulings are contractual decisions, not arbitral awards. So a party usually needs an award or a court judgment to enforce one.
Arbitration or the courts
Arbitration, where a private tribunal both sides agreed on decides the dispute instead of a court, is the usual choice for high-value delay claims. Its awards are easier to enforce under the New York Convention, a treaty under which member countries enforce each other's arbitration awards, and the process stays confidential. Things to know about the arbitration centres:
| Item | Details |
|---|---|
| DIAC (Dubai International Arbitration Centre) | The DIAC Rules 2022 have been in force since 21 March 2022. If the parties haven't agreed on a seat (the arbitration's legal home), the DIFC is the default |
| DIFC-LCIA | Abolished by Dubai Decree No. 34 of 2021. Existing DIFC-LCIA agreements and pending cases moved to DIAC |
| ADCCAC | Replaced by arbitrateAD (Abu Dhabi International Arbitration Centre) for new cases from February 2024 |
The onshore courts still make sense for smaller claims, or when you need the court to order interim measures, temporary orders made before the final decision. Court cases now run under the Civil Procedure Law (Federal Decree-Law No. 42 of 2022), in force since 2 January 2023. It replaced Federal Law No. 11 of 1992.
Court-appointed experts
UAE courts regularly appoint technical experts, and those experts carry a lot of weight. The judge often bases the decision mainly on the expert's report. Parties who do well with delay claims brief the expert fully and early, and they answer the expert's follow-up questions with extra material quickly.

Putting a figure on delay damages
UAE law treats direct damages, your actual losses, differently from consequential damages, the knock-on losses further down the line. There are limits on what you can recover, so plan the claim with care.
Costs you can usually recover
Delay claims in the UAE have recovered:
- extended site overheads such as supervision, security and utilities
- idle equipment costs (depreciation plus financing, but not lost profit)
- higher material prices caused by inflation during the delay
- financing costs for progress payments that came late
- acceleration costs, meaning money you reasonably spent to speed up work and cut the delay
Lost profit on follow-on contracts you weren't awarded is much harder to get. Under the Civil Transactions Code you'd have to prove the "expected gain" with reasonable certainty. UAE courts generally reject global claims, one lump sum for all delays together, when there's no detailed support behind them.
Liquidated damages and set-off
Liquidated damages (LDs) are a sum fixed in the contract that the contractor pays the employer for finishing late. Courts generally enforce the employer's LD clause, but they can adjust the agreed amount. For contracts under the 1985 law, they can bring it in line with the actual loss. Under the 2025 Civil Transactions Law, they can adjust it where the debtor proves the amount was exaggerated or that part of the obligation was performed. So before you claim money of your own, deal with the LDs you face by establishing your right to an extension of time (EOT), extra time to finish without penalty.
The employer should follow the contract procedure when it deducts LDs. If it deducts them without the notice or determination the contract calls for, you can challenge the deduction.
When the big decisions come up
Most delay claims are won or lost at a handful of moments:
Before signing. Negotiate notice provisions you can actually meet, the make-up of the dispute board and the choice of governing law. For complex international projects, consider a DIFC or ADGM seat.
While the work is under way. Set up a system for recording events as they happen. Send protective notices even while relations are friendly. Keep the option of bringing in an expert open.
After completion. Check the limitation period, the deadline for bringing a claim. It's 15 years for civil claims under the Civil Transactions Law and 5 years for obligations between merchants under Article 92 of the Commercial Transactions Law (Federal Decree-Law No. 50 of 2022). Shorter periods may apply to certain bonds and guarantees.
Enforcement. Find out where the other side's assets are before you try to get the award recognized. Take particular care with government bodies, where sovereign immunity can come into play.
Construction Payment Claims in the UAE
Unpaid invoices on a building project can hurt a business more than almost any other dispute in UAE real estate. Main contractors wait on milestone payments. Subcontractors see money held back with no good reason. Either way, knowing how a payment claim works protects your cash flow and keeps the project afloat. Below we follow a claim from the first notice to enforcement, so you can decide what to do before the other side digs in.
When to escalate a payment dispute
Push too hard too soon and you damage the relationship. Wait too long and you lose rights. Use this table as a rough guide:
| Situation | What to do | How urgent |
|---|---|---|
| First missed payment with no explanation | Send a formal demand letter and keep the relationship intact | Watch for 14 to 30 days |
| Payments keep arriving late, or certificates keep being disputed | Give notice of dispute and think about referring it to the DAB | Act at once, because contract time bars apply |
| Termination threatened, or works suspended | Get legal help urgently and seek protective measures | The first 24 to 48 hours count most |
| Retention held back after completion | Challenge the completion certificate and apply for specific performance | Before the limitation period runs out |
Where to go from here
Payment claims reward speed and precision. Whether you get paid or end up writing the money off often depends on acting early and with good information. That's true when you send your first formal claim notice, and it's just as true when you enforce a decision you've won. Specialist legal advice improves your odds at both ends.
Browse our UAE lawyer directory to find a lawyer who handles construction payment claims.
FIDIC Contract Claims in the UAE
Most large building and infrastructure projects in the UAE are signed on FIDIC contracts, a set of standard construction contracts used around the world. When something goes wrong on site, the contract sets out how a claim must be raised, proved and decided. UAE law adds its own rules on top. A contractor hit by delays on a big Dubai project and an employer (the client paying for the works) unhappy with quality in Abu Dhabi both face the same question: how will the claim be handled? The answer can decide whether the project makes or loses money.
What FIDIC contracts are and how UAE law affects them
FIDIC stands for the Fédération Internationale des Ingénieurs-Conseils, the international federation of consulting engineers. It publishes standard form contracts that are now the norm for complex construction projects worldwide. Three of them are common in the UAE. The Red Book (Conditions of Contract for Construction) is for projects the employer has designed. The Yellow Book (Plant and Design-Build) is for projects the contractor designs and builds. The Silver Book (EPC/Turnkey) hands the contractor the whole job, from design and procurement to construction. Together they cover billions of dirhams of construction work every year.
A FIDIC contract doesn't replace UAE law. It sits alongside the UAE Civil Transactions Code, which is Federal Decree-Law No. 25 of 2025, in force since 1 June 2026 and the replacement for Federal Law No. 5 of 1985. The Commercial Transactions Code and rules set by each emirate apply too. Some of these local rules are mandatory, so the parties can't contract out of them. A lawyer who knows FIDIC work in the UAE can tell you where the standard wording stops and where those local rules take over.
Find a UAE law firm that handles construction disputes and knows how to read FIDIC contracts.
The claims that come up most on UAE projects
Construction disputes in the Emirates tend to fall into a handful of groups:
| Type of claim | What it's about |
|---|---|
| Extension of Time (EOT) claims | More time to finish, because of employer instructions, changes to the works, force majeure events such as extreme weather, or COVID-19 disruption |
| Prolongation cost claims | The extra cost of staying on site longer: site overheads, head office costs and financing charges once the job runs past the contract date |
| Variation and change order disputes | Arguments over whether an instruction is a variation under Clause 13, which earns extra pay, or part of the work the contractor already agreed to do |
| Payment and certification disputes | The engineer doesn't certify payment, certifies too little, or the employer doesn't pay |
| Termination claims | An employer ends the contract without good reason, or a contractor walks off the job, under Clause 15 or 16 |
When to escalate a claim
Knowing when to push a dispute further, and when not to, saves a lot of money. These are the usual signs that it's time to escalate:
| Warning sign | What it looks like |
|---|---|
| A biased engineer | The engineer, often appointed by the employer, keeps rejecting sound claims without looking at them properly |
| Payments stop | If certificates or payments are late beyond the periods in the contract, you may have the right to suspend work or terminate |
| The employer may be running out of money | Other contractors are paid late, the press reports problems, or government funding for the project is delayed |
| A limitation period is close | The deadline for bringing a claim will pass whether or not talks are still going on |
Bringing in a disputes lawyer before both sides dig in usually leads to a better commercial result.
Project Variations in the UAE: Notices, Claims and Settlement
A variation is any change to the work a construction contract describes, and variations cause more arguments on UAE building projects than almost anything else. The change might come from a new design, from ground conditions nobody expected or from a client who simply wants something different. How you record it, negotiate it and settle it decides whether you get paid and whether the project stays on schedule. Record it badly and you can lose money even on work you really did. The sections below cover the law, the paperwork and the choices you'll face if a variation dispute starts.
Planning and negotiating a settlement
Most variation disputes end in a deal before anyone gets a final ruling. Good planning helps you recover more and keep the working relationship intact.
Before you start proceedings
Before you file anything, look at (a) how strong your contractual claim is; (b) whether your documents are complete; (c) whether the other side can pay and has assets you could enforce against; (d) how much the ongoing relationship is worth to you; and (e) your exposure to liquidated damages, the fixed sums owed for late completion, if the dispute delays the project. A lawyer usually works this out through a document review and a first estimate of quantum, the amount you can realistically claim.
Writing the settlement agreement
A UAE settlement agreement has to be exact. It should say the claims are settled in full and final; list precisely which claims are released; set out how and when payment is made and what security backs it; cover confidentiality and non-disparagement; and confirm the governing law and which courts or tribunal have jurisdiction. On mainland projects, check whether the settlement needs a VAT (value added tax) adjustment. Leave that out and a fresh dispute can start after the settlement is signed.
On large developments, think about a structured settlement. Payments are linked to milestones and released once the variation work has been checked. The employer carries less risk, and the contractor's cash comes in sooner.
Find a UAE law firm
Decisions you'll need to make
Once a variation dispute starts, some choices can't wait:
When to make things formal
Early in a project, small variations are often sorted out informally to keep everyone working together. But the longer you accept changes without paperwork, the weaker your legal position gets. The turning point often comes when the variations add up to a large share of the contract value, or when payments are late beyond the period the contract allows. From then on, send formal notices and keep full records to protect yourself.
Valuing the claim by cost or by value
UAE law accepts both methods. A cost-based claim asks for what you actually spent plus a reasonable profit. It suits variations that are poorly documented or disputed. A value-based claim asks for what the changed work is fairly worth to the project. It can bring in more where the variation benefits the project, but you'll need stronger evidence. Your lawyer can test both methods against the documents you have.
Security and payment arrangements
If the employer is short of cash, you could accept other forms of security. Options include post-dated checks backed by bank guarantees, an assignment of money that third parties owe the employer, or release of retention in exchange for settling the variations. Each option raises its own questions under UAE insolvency law about enforceability and who gets paid first.
Construction arbitration in the UAE
Building projects in the UAE are huge. Think of the mega-developments on Saadiyat Island or the infrastructure built for Expo City Dubai. They bring together contractors from many countries, joint venture partners and sums that run into billions of dirhams. When a dispute breaks out on a job like that, it almost always goes to arbitration, where a private tribunal both sides agreed on decides the case instead of a court. The UAE has set out on purpose to become the region's centre for this, and its rules try to keep cases quick enough for business while giving the parties legal certainty.
Below, you'll find the whole route a construction arbitration takes in the Emirates, from the moment a claim takes shape to enforcing the final decision, which is called the award.
How long each stage takes
If you know the rough timing, you can make better business decisions about the case.
The usual stages of an arbitration
| Phase | Time frame | What happens |
|---|---|---|
| Forming the tribunal | Depends on the rules and on any challenges | Arbitrators are appointed, challenges are decided, terms of reference are agreed |
| Written pleadings | Set in the procedural timetable | Statement of Claim, Defence, Replies and Sur-Replies |
| Document production | Set in the tribunal's timetable | Redfern schedules (tables of document requests and objections), privilege claims, translations |
| Expert reports and expert meetings | Set by the tribunal after hearing from the parties | Experts give evidence one after the other or together, which is called hot-tubbing |
| Hearing | Depends on the witnesses and experts | Witnesses testify, experts are questioned, both sides make closing submissions |
| Award | Under the DIAC Rules, within 6 months of the file reaching the tribunal unless extended (Article 35) | The tribunal deliberates, writes the award and issues it |
Nobody publishes official figures on how long complex construction arbitrations take in the UAE, and every case is different. If you need a faster result, most institutional rules have a fast-track procedure you can ask for.
Decisions you'll face along the way
Some choices during the case have a big effect on the result and on what it costs you.
When to settle
Many construction disputes settle before the final award. Two moments often work well. One is after the first pleadings, when both positions have become clear. The other is after the expert reports, when you can see the likely range of the money claim. An honest early assessment from lawyers who have run construction cases before helps you judge any offer.
Choosing the arbitrators
Who sits on the tribunal shapes the whole case. Think about:
- The balance between technical and legal backgrounds
- Training in civil law, where judges work mainly from written codes, or in common law
- Earlier experience in the construction industry
- Whether they have time for your case and how they run proceedings
- Appointment through an institution or ad hoc between the parties
Costs and funding
Construction arbitration is expensive. You pay the tribunal, the institution, your lawyers, the experts and the hearing rooms. Third-party funding, where an outside funder pays the costs in return for a share of any money won, is more and more available in the UAE, although the rules on it are still taking shape. It's also worth asking your lawyers about fixed fees or fees linked to success.
Related Resources
More from our real estate and construction law section:
- Construction Defects Liability UAE: quality obligations and decennial liability
Frequently Asked Questions
I missed the notice deadline but told the engineer verbally. Can I still recover delay costs?
Usually not. UAE courts apply written notice requirements strictly. Contractors in this position sometimes argue that (1) the employer knew about the delay anyway through other channels, (2) the employer waived the requirement by the way it behaved, or (3) the notice clause conflicts with mandatory law. Whether any of these works depends on the facts. Confirm every verbal conversation by email straight away, and ask a construction lawyer whether a waiver argument is open to you.
How does concurrent delay affect what I can claim in a UAE dispute?
Concurrent delay means you and the employer both caused delay over the same period. UAE civil law has no clear rule on it. Courts usually split responsibility according to the evidence on causation, which tends to reduce your recovery rather than wipe it out. Common law courts often look for the "dominant cause". UAE tribunals, by contrast, may award part of the compensation in proportion to the delay the employer caused. A careful schedule analysis that separates excusable, compensable and non-compensable delay periods makes your case for that split stronger. Excusable delay earns you more time, and compensable delay earns you money as well.
What evidence shows COVID-19 was force majeure for delays during the pandemic?
Helpful evidence includes (1) specific government restrictions that hit your project (a general lockdown announcement isn't enough), (2) proof that alternatives such as shift work or changes to the supply chain were impossible, (3) records of what you did to limit the delay, and (4) figures showing that the delay you claim was longer than any concurrent delay you caused. Tribunals are now skeptical of general COVID-19 claims, so you need causation evidence tied to your own project.
Can a subcontractor bring a delay claim directly against the developer?
Not on a contract, as a rule. Privity, the principle that only the parties to a contract can sue on it, generally blocks a direct contractual claim. A subcontractor may still find a way through (1) nominated subcontractor provisions that set up a three-way arrangement, (2) a tort claim for a specific harmful act (this seldom succeeds), (3) an assignment of the main contractor's claims, or (4) collateral warranties, if any were signed.
How do UAE courts treat "global claims" without detailed proof of causation?
A global claim lumps the effect of several delays into one figure, and it's at high risk of rejection because you must show causation. Your chances are better where (1) keeping records was truly impossible because the employer obstructed you, (2) the global part is a small share of the total damages and the rest is supported in detail, or (3) the employer's breach was so serious that a rough figure is the fair answer. Even so, always try to allocate costs event by event. A global claim remains a high-risk approach and needs an exceptional reason.
How is a delay claim in the DIFC Courts different from one in the onshore Dubai courts?
In the DIFC you plead to common law standards and must give detailed particulars. Disclosure is wide and includes documents that hurt your own case. Witnesses give evidence and are cross-examined, and the losing side usually pays the winner's costs. Onshore courts rely more on documents and on investigation by court-appointed experts. Outside the DIFC, DIFC Courts judgments are executed through the Dubai Courts' execution judge (Article 32 of Dubai Law No. 2 of 2025).
When should I bring in a delay analysis expert?
Ideally while the project is running, so the analysis follows events as they happen. At the latest, before you submit the formal claim. UAE tribunals and courts may give less weight to an analysis done after the fact purely for the case. An expert who joins early can set up proper record-keeping, update the schedule as delays hit and give you a credible first assessment for settlement talks. Expert evidence often decides the outcome.
Can I still claim delay damages after accepting final payment or signing a completion certificate?
Final account settlements and taking-over certificates (the document confirming the employer has accepted the works) often contain discharge wording that bars later claims. UAE courts will look at whether (1) the claim was known and reserved, (2) fraud or a shared mistake affected the settlement, or (3) the certificate expressly left certain claims out. Put reservation of rights wording into the close-out documents while you negotiate them, and never sign a final document until someone with legal training has checked what it discharges.
How is an extension of time (EOT) valued when delays hit several activities at once?
You have to show that the activities that ran longer were actually on the critical path during the delay. Float matters a great deal here. It's the spare time an activity has before it holds up the finish date. A delay to an activity that still had float may not earn you extra time, even though it cost you money. Tribunals often accept a windows analysis, which looks at the schedule in slices of time to show how the critical path shifted. In lower-value disputes, simpler methods are still preferred.
What problems come up when enforcing a delay award against a UAE government body?
Projects for federal and emirate governments raise questions of sovereign immunity, which limits legal action against the state. The UAE is a party to the ICSID Convention and acceded to the New York Convention in 2006. Even so, execution against government assets is restricted, and public property can't be attached. Security such as mortgages and guarantees, along with advance payment bonds, is a safer bet than relying on the award alone.
Can I get paid for work I did without a written contract?
Yes. UAE courts can award the value of construction work done without formal paperwork, for example under the contract rules on remuneration or the unjust enrichment rules of the Civil Transactions Law. Unjust enrichment means nobody may gain at someone else's expense without a legal reason. Proving the scope, the rates and the employer's acceptance is much harder, though. You'll need to show (1) that the employer asked for the work or went along with it, (2) that you actually did it, and (3) what it was reasonably worth. Emails, site instructions, progress photos and witness statements carry a lot of weight here. Expect to recover less than contract rates would have paid, and expect long arguments over the evidence.
What happens if I miss the contract's notice deadline for a payment claim?
UAE courts and arbitral tribunals often apply contractual time bars, depending on the wording and the facts. Miss a 28-day notice window and you'll usually lose that particular claim. Related claims with their own triggering events may survive. Exceptional cases, such as fraud by the employer or force majeure that made notice impossible, may justify more time, but the outcome is uncertain. Get legal advice as soon as you spot the missed deadline, so someone can check what options are left.
Can I get back what it cost me to prepare a FIDIC claim in the UAE?
Usually not. FIDIC contracts don't give you an express right to recover the cost of preparing a claim. If the employer acted unreasonably in turning down a claim that was clearly sound, a tribunal may weigh that when it decides who pays the costs. Keep a record of the work that went into the claim anyway, because it can affect the overall costs award in an arbitration.
What if the engineer won't issue a taking-over certificate so that my claim stalls?
This happens a lot on UAE projects. The taking-over certificate confirms that the works are complete enough for the employer to take them over. Under FIDIC Clause 10.1, the engineer has 28 days from the contractor's application to issue it or to give detailed reasons for refusing. A refusal that keeps going without good reason can be treated as a breach by the employer. Contractors can refer the matter to the DAAB. In urgent cases, they can ask the competent court or tribunal for interim measures, temporary orders made before the final decision, to force the certificate to be issued.
Checklist for a construction delay claim
- Read the notice clauses in your contract and put every deadline in the calendar with time to spare
- Send protective notices for every possible delay event, including ones you're unsure about
- Keep records as events happen, with photos
- Keep the baseline schedule and every revision, together with proof that each was approved
- Bring in delay analysis help before the claim takes shape, not after
- Think about where a dispute would be heard (DIFC, onshore courts or arbitration), both before signing and once a dispute arises
- Put a figure on each category of loss, backed by invoices, payroll records and equipment logs
- Work out how much in LDs you could owe, and plan your EOT case before you claim money of your own
- Record everything you did to reduce the delay and what it cost
- Talk to a construction delay claims lawyer before you settle the final account or accept a certificate