An arbitration clause in your contract means a dispute doesn't go to court. It goes to arbitration, where a private tribunal both sides agreed on decides the case. When a dispute breaks out, the party with the claim has to open that process the right way. A mistake in the first filing can cost months, and some mistakes make the final decision hard to enforce. This page explains what the filing involves, which rules apply and where people tend to slip up. Find a UAE law firm if you'd like someone to check your papers before they go in.
Key Takeaways
- Your filing has to follow the UAE Arbitration Law (Federal Law No. 6 of 2018) and, if an institution runs the case, that institution's own rules.
- Get the papers and the timing right. A faulty first filing can hold the case up or leave you with an award, the tribunal's final decision, that a court won't enforce.
- The institution you pick has a big say in your timetable and your costs. The usual options are the Dubai International Arbitration Centre (DIAC), arbitrateAD in Abu Dhabi and the International Chamber of Commerce (ICC).
- A lawyer who sees the file early can catch procedural errors before they weaken your case.
- UAE courts keep a small but real supervisory role. They can order urgent interim measures, and they ratify awards before enforcement.
Which law governs your arbitration
UAE law lets the parties shape their own arbitration, and the courts step in only at fixed points. How to word the arbitration clause itself is covered in a separate guide in this hub, Arbitration Clause Drafting UAE. This page picks up later, once the dispute has arisen and you need to start formal proceedings.
The federal Arbitration Law
Federal Law No. 6 of 2018, usually just called the Arbitration Law, governs every commercial arbitration outside two financial free zones: the Dubai International Financial Centre (DIFC) and Abu Dhabi Global Market (ADGM). The law is based on the UNCITRAL Model Law, a template written by the United Nations Commission on International Trade Law that many countries have adopted. These are the provisions that matter most when you file:
- Articles 4 to 7: who has the capacity to agree to arbitration, and the form and writing a valid arbitration agreement needs
- Article 27: when the arbitration officially begins
- Article 30: what goes into the statement of claim and the statement of defence
- Articles 9 and 11: how many arbitrators sit and how they're appointed
The two financial free zones have their own systems. The DIFC has its own Arbitration Law (DIFC Law No. 1 of 2008). ADGM applies its Arbitration Regulations 2015, which are also based on the UNCITRAL Model Law. Before a single document is submitted, you need to know which of these regimes applies to your case.
Institutional or ad hoc arbitration
An early choice decides how every later step works. In institutional arbitration, a centre such as DIAC administers the case under its published rules. In ad hoc arbitration, there's no centre and the parties run the process themselves. Here's how the two compare.
| Factor | Institutional Arbitration | Ad Hoc Arbitration |
|---|---|---|
| Who handles the admin | The centre's secretariat does all of it | The parties do it themselves |
| Appointing arbitrators | The institution helps if the parties can't agree | The parties must agree, or ask a court to step in |
| How predictable the timetable is | Set procedural schedules | Flexible, but it can be uncertain |
| Costs | You pay administrative fees | Lower direct costs, but more work to manage |
Onshore, meaning outside the financial free zones, the two main centres are DIAC and the Abu Dhabi International Arbitration Centre (arbitrateAD). arbitrateAD replaced the Abu Dhabi Commercial Conciliation and Arbitration Centre (ADCCAC) from 1 February 2024. DIAC also absorbed DIFC-LCIA, the former DIFC centre linked to the London Court of International Arbitration, when Dubai Decree No. 34 of 2021 moved its functions to DIAC. Each centre has its own filing requirements and fee table, so read the ones that apply to you.
How the filing works, step by step
Most arbitrations in the UAE open in the same order. The exact timing depends on the institution and on how complicated the dispute is.
Stage 1: Check your position before you file
Before anything is submitted, someone has to look closely at the case. That review usually covers:
- whether the arbitration agreement is valid and actually covers this dispute
- the limitation period, the deadline for bringing a claim under UAE law, and whether it's still open
- the best seat and the applicable law (the seat is the arbitration's legal home, which decides which court supervises it)
- which evidence needs to be secured now
- whether arbitration or a court case makes more financial sense
It's also worth asking whether you need urgent help from a court. Under Article 18 of the Arbitration Law, UAE courts can grant conservatory relief, meaning orders that hold assets or evidence in place, even before the arbitration formally starts. When you apply matters, so plan it.
Stage 2: Draft and file the Request for Arbitration
The Request for Arbitration, sometimes called the Notice of Arbitration, is the document that formally starts the case. It must meet the requirements of the law and of the institution's rules. A typical Request includes:
- full details of each party and of anyone representing them
- the arbitration agreement, quoted in full or described
- a clear statement of your claims and the facts behind them
- the remedy you're asking for, with damages put into figures
- how many arbitrators you propose and how they should be appointed
- the arbitrator you nominate, if you have the right to nominate one
- a first estimate of the contract value in dispute, which the institution uses to calculate its fees
A fee is due with the filing. DIAC charges a registration fee of USD 3,000 under its 2025 Table of Fees and Costs, payable in AED (as of October 2026). It won't register a Request until that fee is paid, however complete the documents are (Article 4.4 of the DIAC Rules). arbitrateAD wants a non-refundable filing fee of AED 10,000 along with the request (Article 49 and Annex 1 of its Rules).
Stage 3: The respondent's Answer and any counterclaims
After the filing goes through, the institution notifies the respondent, the party you're bringing the claim against. The respondent usually has 30 days to send an Answer. That Answer has to deal with:
- whether it admits or denies each part of the claim
- any objection that the tribunal has no jurisdiction to hear the case
- the arbitrator the respondent nominates
- any counterclaims, set out in full
The arguments on the substance only begin once these first exchanges are over and the whole tribunal has been formed.
Documents to gather before you submit
Missing or faulty paperwork is the most common reason a filing gets delayed. Have the following ready before you file.
The core documents
- the signed arbitration agreement, or the contract that contains the arbitration clause
- registration documents for every company involved, such as trade licenses and commercial registrations
- a power of attorney that authorizes your lawyers to act for you
- evidence that supports your damages figures
- correspondence that shows the dispute exists
Getting foreign documents accepted
Foreign companies face an extra hurdle. A document issued outside the UAE usually has to go through these steps:
- A notary in the country where it was issued notarizes it.
- That country's foreign ministry attests it (in some countries this is done by apostille, a standard certificate). The UAE embassy or consulate in that country then legalizes it, and the UAE Ministry of Foreign Affairs attests it. The longer chain is needed because the UAE isn't a party to the Hague Apostille Convention.
- A translator approved by the UAE Ministry of Justice prepares a certified Arabic translation.
All of this can add several weeks to your preparation. Start on it early, so you aren't chasing stamps in the last days before filing.
How long each phase takes
Every arbitration moves at its own pace, so it's hard to give fixed durations. The table lists the main phases and what makes each one shorter or longer.
| Phase | Time frame | What affects the timing |
|---|---|---|
| Preparing the filing | Depends on the case | Whether the documents are at hand, and whether they need attesting |
| From registration until the tribunal is formed | Depends on the rules (at DIAC, the Answer is due 30 days after the Request is notified) | How many arbitrators there are, and any challenges to their appointment |
| From the case management conference to the final hearing | Set by the tribunal's procedural timetable | How complex the case is, the number of witnesses, any expert evidence |
| The award after the hearing | Under the DIAC Rules, the final award is due within 6 months of the file reaching the tribunal, unless extended (Article 35) | How busy the tribunal is, and how complex the award is |
The case management conference is the first procedural meeting, where the tribunal and the parties settle how the case will run. Smaller disputes can often take a faster route. Most institutions offer an expedited procedure for claims below a set value. At DIAC, for example, it applies when claims and counterclaims together come to AED 1,000,000 or less. The final award is then due within 3 months of the file reaching the tribunal, unless that's extended (Article 32).

Decisions the client has to make
Your lawyers can handle the routine approvals. A few questions, though, need an answer from you as the business owner.
Where the arbitration is seated
The seat decides which courts supervise the arbitration and which law governs its procedure. Dubai and Abu Dhabi are the usual seats. Other emirates have centres as well, such as the Sharjah International Commercial Arbitration Centre (Tahkeem). Each seat has its own consequences for enforcing the award later, so ask how your choice would play out.
How many arbitrators, and who they are
No rule says a dispute above a certain value needs three arbitrators. The DIAC Rules start from a sole arbitrator, unless the parties agree otherwise or the DIAC Arbitration Court decides three are appropriate (Article 10.2). The Arbitration Law starts from the other end. It provides for three arbitrators where the parties haven't agreed on a number and the Relevant Authority (the body the law gives this kind of decision to) doesn't decide otherwise (Article 9). You'll be asked to decide:
- whether you want arbitrators who specialize in your industry or generalists
- what nationality and language skills you'd like them to have
- whether you accept the candidates put forward to chair the tribunal
Keeping the case confidential
Unlike a UAE court case, arbitration is private by its nature. You can add further protection with an express confidentiality undertaking. It can go into an early procedural order. Some rules, such as the ICC Rules, use Terms of Reference, a document drawn up at the start that sets out the issues and the procedure, and the undertaking can go there instead.
When UAE courts get involved
An arbitration is a private process, yet UAE courts still play a defined part in it. Knowing where they come in tells you when you may need a judge.
Court help before or during the arbitration
Article 18 of the Arbitration Law lets you ask the president of the court for interim measures, temporary orders that protect your position until the dispute is decided. You can apply before the arbitration starts or while it's running. The usual requests are:
- orders freezing assets
- orders preserving evidence
- orders keeping things as they are while the dispute is pending
Enforcing the award after you win
A successful arbitration ends with an award you can enforce, which means getting a court to make the losing side actually pay. The ratification process, where a court formally approves the award, is explained in our guide to Arbitration Award Enforcement UAE. In short, an award made in the UAE needs court ratification under Articles 52 and 55, and the court has to decide within 60 days of the request. A foreign award goes through the New York Convention, a treaty under which member countries enforce each other's arbitration awards.
Filing mistakes that cause trouble later
Large, experienced companies make these mistakes too. Each one can be avoided if you check for it in time.
| Item | Details |
|---|---|
| A badly drafted arbitration clause | Lawyers call these pathological clauses. When the wording is so unclear that the tribunal first has to work out what it means, the case slows down. |
| Naming the wrong party | If you name the wrong legal entity, the award is void against the company you actually meant to pursue. |
| Missing the limitation period | UAE limitation periods apply whatever the arbitration agreement says. Civil claims generally have 15 years under the Civil Transactions Law. Claims between merchants over commercial obligations have 5 years (Article 92 of the Commercial Transactions Law, Federal Decree-Law No. 50 of 2022). |
| Damages not properly worked out | A vague claim draws procedural objections, and you may end up recovering less. |
| Not preserving evidence | Look early at the UAE rules on keeping documents, and at the risk of evidence being lost or destroyed (lawyers call this spoliation). |
Questions about filing for arbitration in the UAE
Can I start an arbitration if the other side has already sued in a UAE court?
Yes, as long as your contract has a valid arbitration clause. File your arbitration promptly and, at the same time, ask the court to dismiss the lawsuit under Article 8 of the Arbitration Law. Article 8(1) says the court must declare the action inadmissible if you raise this objection before making any claim or defence on the merits, meaning the substance of the dispute. The only exception is where the court finds the agreement null and void or incapable of being performed. If you wait until after your first defence on the substance, you risk losing the right to arbitrate.
What happens if the respondent ignores the notice of arbitration?
The case goes ahead without them. The institution appoints the arbitrators in the respondent's absence, and the tribunal can issue an award by default, without the respondent taking part. Courts do look harder at default awards when you try to enforce them. Keep a careful record proving the respondent was properly served, and keep inviting them to take part in good faith. That protects the award when you come to enforce it.
Are there special rules when a government body is on the other side?
Federal and emirate-level government bodies are agreeing to arbitration more often than they used to, but they may need specific authorization first. Some can't take part without approval from the Cabinet or the Ruler's Court. Check that your counterpart has the power to arbitrate before you file. Without proper authorization, the award may turn out to be unenforceable against a sovereign party.
Can I change my claims after the first filing?
Yes, but the institution's rules limit how. Under the DIAC Rules, once the statement of claim, the statement of defence and any counterclaim are in, a new claim needs the tribunal's permission or the agreement of the parties. Any increase in the amount claimed is reported to the Centre so it can adjust its fees (Article 24). Late changes that upset the timetable can count against you when costs are decided. It's far easier to set out the full claim at the start than to keep revising it.
How does the DIAC restructuring affect cases already filed?
Dubai Decree No. 34 of 2021 abolished two bodies: the DIFC Arbitration Institute, which ran DIFC-LCIA, and the Emirates Maritime Arbitration Centre. Their functions went to DIAC. Cases that were already pending carry on under their existing rules unless the parties agree otherwise. The 2022 DIAC Arbitration Rules came into force on 21 March 2022 and apply to new cases started after that date. Ask the institution which rules apply to your case, because timetables and fees differ a good deal between rule sets.
Can I get urgent relief before the full tribunal is in place?
At DIAC you can. Its 2022 Rules introduced the emergency arbitrator, a single arbitrator appointed at short notice to deal with urgent requests. The Centre aims to appoint one within 1 day of an application that meets the requirements, and the emergency arbitrator sets a timetable within 2 business days (Appendix II, Articles 2.5 and 2.9). The option exists for situations where waiting for the full tribunal could cause harm that can't be undone. An emergency arbitrator's order binds the parties for the time being. The emergency arbitrator's powers end once the tribunal is formed, and the tribunal can discharge the order (Appendix II, Articles 2.12 and 2.13). Not every UAE institution offers the same thing, so check before you choose where to file.
What language do arbitration filings have to be in?
The parties decide, either in their agreement or later on. If they haven't agreed, the DIAC Rules use the language of the arbitration agreement to begin with and leave the final decision to the tribunal (Article 21). For proceedings it governs, the Arbitration Law makes Arabic the default (Article 29). Anything you file with a UAE court, for interim relief or for enforcing the award, needs a certified Arabic translation. Put translation and possibly interpreters into your budget from the start.
Can the hearings take place online?
Since the pandemic, all the major UAE institutions have allowed virtual hearings, and DIAC's 2022 Rules deal expressly with electronic proceedings. Some evidence still works better in the room, especially when the tribunal has to judge whether a witness is believable. Settle the technical arrangements early, for example in the proposed Terms of Reference, so they don't become a separate argument later.
Who pays the costs of an arbitration in the UAE?
Institutional costs are made up of the registration fee, administrative fees and the arbitrators' fees. The parties usually pay these in advance in equal shares. At the end, tribunals generally follow the "loser pays" principle. They can depart from it, depending on how each party behaved and how far each one succeeded. In complex cases, file a detailed costs submission together with your claims, which makes it easier to get your money back later.
How is a DIFC-LCIA filing different from a DIAC case?
You can't file a new case with DIFC-LCIA any more. Dubai Decree No. 34 of 2021 handed its functions to DIAC, and pending DIFC-LCIA cases carry on under their existing rules with DIAC supervising them. Arbitrations seated in the DIFC are still supervised by the DIFC Courts. Enforcement takes different routes too. Awards from DIFC-seated arbitrations are recognised by the DIFC Courts and then executed onshore through the Dubai Courts. Awards from arbitrations seated onshore in Dubai are ratified by the Dubai Court of Appeal. Which of these applies depends on the details of your dispute.

Choosing Arbitrators in the UAE: Legal Conditions, Checks and Deadlines
Paperwork and filing
What to check before you nominate
Look closely at each candidate before you put their name forward. Ask for these documents and read them properly:
- A CV and a disclosure statement. Standard arbitrator CVs often leave out earlier appointments and relationships. Ask for the institution's disclosure statement, which should list pending and past arbitrations, professional links with the parties and their lawyers, and any financial interests.
- Earlier awards. Where they're public, they show how the arbitrator reasons and runs a case, and whether that fits your approach.
- Written confirmation of availability. Institutional rules usually make arbitrators confirm they have time. In an important case, get a written confirmation that goes beyond the standard form.
- The fee basis. DIAC fixes arbitrator fees by reference to the amount in dispute under its Table of Fees and Costs. Check the schedule that applies, and ask for a fixed-fee proposal where the rules allow one.
- Professional indemnity insurance. Arbitrators don't have to carry it, but having it says something about their standing and gives you a route to compensation for procedural misconduct.
Filing the nomination
Institutions set tight deadlines for nominations. Under the DIAC 2022 Rules, the claimant names its arbitrator in the Request for Arbitration, and the respondent nominates within 30 days of receiving the Request. Miss the deadline and the institution can appoint an arbitrator without asking you, which advisers in this field try very hard to avoid.
You'll usually need to file:
- a signed statement of independence and impartiality
- a CV that discloses any relationships with the parties or their lawyers
- the arbitrator's acceptance of the appointment terms
- a fee proposal, or confirmation that the institution's fee schedule applies
- proof that required training has been completed (only for certain specialist panels)
Challenging an arbitrator
When the law allows a challenge
Article 14 of the UAE Arbitration Law allows you to challenge an arbitrator in only two situations. The first is when circumstances raise serious doubts about their impartiality or independence. The second is when they don't have the qualifications the parties agreed or the law requires. The law doesn't list specific relationships, but Article 10(1)(c) rules out an arbitrator with a direct relationship to a party that would damage their impartiality, integrity or independence.
Challenges in the UAE often come up in situations like these:
- the arbitrator is also acting as a lawyer, in an unrelated case, for a company in the same group as one of the parties
- the arbitrator once worked as an expert witness for a party's affiliate and didn't say so
- social or professional ties inside the UAE's small legal community
- the arbitrator has published an academic or professional opinion on a legal question that's in dispute
How a challenge works and how fast you must act
The deadlines are short, so you have to move at once. A written challenge must be filed within 15 days of learning of the problem, or within 15 days of the appointment if you knew about it before then. The arbitrator may step down. If not, the institution or the competent court decides.
Under the DIAC Rules, the DIAC Arbitration Court decides challenges (Article 15.3). Under the arbitrateAD Rules, the arbitrateAD Court first asks the challenged arbitrator and the other arbitrators for comments (Article 16.3). Old DIFC-LCIA cases now run under DIAC supervision because of Dubai Decree No. 34 of 2021, and that's worth keeping in mind when you plan nominations.
Under Article 15(2) of the Arbitration Law, the Relevant Authority (the institution or the court) decides the challenge within 10 days, and you can't appeal its decision. This is why careful checks before the appointment protect you better than a challenge afterwards.
Emergency arbitration in the UAE
An emergency arbitrator can freeze a situation within days, long before the full arbitration panel has even been chosen. That matters when the other side is moving money out of reach, is about to leak confidential information or is breaking a contract in a way that can't be undone later. In the UAE the procedure differs depending on whether your contract falls under onshore federal law or one of the financial free zones, and the paperwork has to be ready almost at once.
Documents and evidence you'll need
You'll be putting the file together under heavy time pressure, and the arbitrator will read it critically. Build it so it holds up against the objections the other side is likely to raise.
What goes into the file
| Category | What you need | Where applications go wrong |
|---|---|---|
| The contract | The signed arbitration agreement, the main contract and any amendments | Unclear wording on emergency arbitrators, or a pathological clause (one so flawed it can't work as written) |
| Proof of urgency | A timeline of events, messages showing the harm is about to happen, notices from third parties | General allegations with no dates and no figures for the loss |
| Irreparable harm | Financial analysis, expert opinions on damage that money can't make good, market conditions | Claims where a payment of damages would plainly be enough |
| Prima facie case | The important correspondence, performance records, documents proving the breach | Arguing the whole case on the merits when the evidence so far is thin |
| Precise relief | Draft orders ready to sign, with details of how they'd be carried out | Broad or vague requests that an arbitrator can't realistically enforce |
Arbitrators see the same gaps again and again. Someone who knows the institution's standards can read your file the way the respondent's lawyers will and close those gaps before you submit.
Common problems and how to handle them
Even a well-prepared application can run into trouble. If you know the usual problems in advance, you can react faster when one appears.
The respondent avoids notice or won't take part
Most institutional rules let the emergency procedure go ahead in absentia, which means without the respondent. The arbitrator may still want extra proof that notice really reached them. Keep detailed records of how the papers were served, and use more than one channel to notify the other side.
The respondent goes to court at the same time
Respondents sometimes start a competing court case to derail the emergency arbitration. Under a principle called kompetenz-kompetenz, arbitrators can generally decide for themselves whether they have jurisdiction over a dispute. Even so, your arbitration lawyer and your litigation lawyer should coordinate from the start so they don't take conflicting positions.
The other side fights enforcement
Opposing parties often resist enforcement by arguing that the order offends public policy or that the procedure was irregular. If the order is drafted from the outset with clear, measurable terms, they have much less to work with.
Shareholder Arbitration in the UAE
When the owners of a UAE company fall out, the case often goes to arbitration instead of court, because the shareholders' agreement says it must. Arbitration is a private process. A tribunal that both sides agreed on decides the dispute in place of a judge, and the hearings stay confidential. Below you'll find how the rules work, what a good clause contains, how a case runs and how you collect on the result.
Writing a shareholder arbitration clause that works
A standard arbitration clause copied from another contract often misses the problems that are typical of company disputes. A clause written for your shareholders' agreement heads off most of the later arguments.
What the clause should cover
A good clause deals with the following.
Which disputes it covers. Keep the definition wide, for example "any dispute arising out of or in connection with this Agreement, including disputes regarding interpretation, termination, breach, shareholder rights, director duties, valuation, and deadlock resolution." A narrow definition invites side cases over whether a particular claim can be arbitrated at all.
Steps before arbitration. Many shareholder agreements set out a ladder, for example: (1) talks between senior managers (30 to 60 days); (2) mediation under named rules; (3) arbitration. The early steps give the business relationship a chance to survive, and the last step still guarantees a decision.
Who can sit as arbitrator. You can set requirements such as "minimum 15 years' experience in UAE corporate law," "qualified in common law and civil law jurisdictions," or "experience in business valuation." Civil law is the system where judges work mainly from written codes. Rules like these keep out generalists who aren't equipped for a technical shareholder fight.
Seat and governing law. The seat decides which procedural law applies and which court supervises the case. Common choices are Dubai (mainland or DIFC) and Abu Dhabi (mainland or ADGM, the Abu Dhabi Global Market). International joint ventures sometimes pick a neutral city like Singapore or London.
When several contracts and parties are involved
A shareholder dispute rarely touches just one document. There's the shareholders' agreement, the articles of association, perhaps a management agreement and the financing papers. If each one has a different arbitration clause, you can end up with parallel cases and long arguments about which clause applies.
The fix is to use the same arbitration wording in all of them and to have every party agree in advance that related disputes can be heard together. The 2022 DIAC Rules let cases be consolidated and extra parties be joined (Articles 8 and 9), and lawyers in shareholder cases rely on these powers more and more.
Decisions you'll need to make
Some choices come up again and again as a shareholder dispute develops. These are the main ones.
Arbitration or court
Arbitration gives you confidentiality, arbitrators who know the subject, flexible procedure and awards that are easier to enforce abroad. On the downside, your rights of appeal are limited, the costs can be higher, and pulling several parties into one case is harder. In some situations court is the better route. A lawyer who handles shareholder disputes can tell you which way your own case points.
With an institution or ad hoc
In institutional arbitration a centre such as DIAC runs the case, appoints arbitrators where needed and keeps costs in check. That helps if you've never been through an arbitration before. In ad hoc arbitration the parties run it themselves. It's more flexible and can be cheaper for experienced parties who already know each other well. Shareholder cases are usually complicated, so for most of them an institution is the better choice.
Urgent and interim relief
Shareholder disputes often need quick action, for example to stop company assets from disappearing or to block a harmful decision. Modern institutional rules let an emergency arbitrator grant interim relief within days of an application. You can also apply to a court at the same time under Article 18 of the Arbitration Law. Once the tribunal is in place, though, courts often leave these questions to it.
Settling the dispute
Many international arbitrations settle before the final award. Shareholder disputes are especially likely to, because the parties usually still depend on the same business. The tribunal can record the settlement as a consent award, which can be enforced in the same way as an award after a full hearing.
To talk through your case with a lawyer, search our law firm directory for a UAE firm that handles shareholder arbitration.
International arbitration in the UAE
When a cross-border deal with a UAE company goes wrong, or a contract signed in the Emirates ends in a dispute, the case now usually goes to arbitration rather than to court. Arbitration means a private tribunal that both sides agreed on decides the dispute. Dubai and Abu Dhabi both want to be global centres for this work, so there are several institutions and seats to pick from. Before you sign a clause or start a case, it pays to know how they differ and what each choice means when you later try to collect.
Documents and filings
What a valid arbitration agreement needs
UAE law requires the arbitration agreement to be in writing (Article 7), and both parties must clearly consent. If you agree to arbitrate after the dispute has already started, the agreement must also spell out which matters go to arbitration (Article 5(2)). Check that you have:
- A clear clause naming the institution, the seat, the language and the governing law
- Signatures that meet UAE authentication rules, so the award can be enforced later
- Proof that the signatory had authority, such as a board resolution or power of attorney
- Notarization and legalization for agreements signed abroad that you may need to enforce in the UAE (a notary confirms the signature and the authorities stamp it so UAE offices accept it)
Statement of claim and defence
Your first filings have to satisfy the institution's rules as well as what UAE procedure expects. The statement of claim, the document that sets out your case, should cover:
- The facts, told in strict date order
- The legal basis for each claim under the law that governs the contract
- The damages you claim, with figures and an explanation of how you got them
- Documentary evidence, organized as indexed exhibits
- Summaries of what your witnesses and expert witnesses will say
The defence needs the same discipline, answering each point and putting forward counter-evidence. Experienced arbitration teams start organizing documents early, because UAE proceedings often involve large hard-copy filings.
Power of attorney
UAE courts and arbitral institutions are strict about powers of attorney. A foreign company has to sign a notarized and legalized power that specifically authorizes someone to represent it in the arbitration. For enforcement onshore, you also need Arabic translations certified by translators approved by the UAE Ministry of Justice.
Choices you'll have to make
Picking the seat
To decide between an onshore UAE seat, the DIFC and ADGM, look at:
- Where the other side's assets are and where you'll most need to enforce
- Whether you might need interim relief from the national courts
- How much confidentiality you need (the DIFC Arbitration Law makes all information on the proceedings confidential, Article 14)
- Which language you'd like to use and how much you can spend on translation
- How complicated the governing law is, and whether arbitrators who know it are available
One arbitrator or three
This comes down to cost against benefit. A sole arbitrator is cheaper and gets smaller cases finished sooner. For high-value or technically complex disputes, parties often prefer three arbitrators, so the panel brings a wider mix of knowledge.
How much document disclosure to expect
UAE arbitrations used to involve far less disclosure of documents than common law court cases. Institutions are now moving toward broader document production. Assess your case early and put a litigation hold in place, an instruction to staff not to delete or discard anything relevant.
Checklist before you file
- ☐ Find the arbitration clause in the underlying contract and read it closely
- ☐ Check that the limitation period under the applicable law hasn't run out
- ☐ Confirm the correct legal name of every party to the dispute
- ☐ Choose the arbitration institution and confirm which rules apply
- ☐ Prepare a complete Request for Arbitration, with all damages put into figures
- ☐ Have every foreign document attested and translated
- ☐ Sign powers of attorney for each of your legal representatives
- ☐ Pay the institution's registration fee
- ☐ Decide whether you need interim relief from a court before the arbitration begins
- ☐ Instruct a verified UAE law firm that has handled arbitrations before
- ☐ Make sure nothing relevant gets deleted: set up document preservation and send litigation hold notices to staff
- ☐ Draw up a first budget for the case, including the other side's costs you might have to pay if you lose
Most of the work in an arbitration happens before the Request reaches the institution. What you decide at this stage follows the case all the way through, from how fast it moves to how much you finally recover. If the clause, the party names, the deadlines and the papers are checked before you file, you avoid most of the problems described on this page.
More Legal Guides